A whole-house renovation in a Selangor terrace, semi-D or bungalow involves many trades: hacking, plumbing, wiring, plaster ceiling, carpentry, painting, flooring, stairs and often the porch and garden. Each one is straightforward on its own. The trouble usually comes from the order. A new floor installed too early can be scratched by ladders, splashed with paint or dented by carpentry. Installed too late, it may hold up cabinets or force awkward cuts.
This guide sets out a practical renovation order of works for a landed home, shows where flooring fits, and explains how to protect it until you move in. Every project is different, so treat this as a starting point to discuss with your contractor.
Planning a whole-house renovation?
Send us your area, house type and the rooms you want floored. We’ll suggest where flooring fits in your contractor’s timeline.
A Typical Order of Works
| Step | Work | Why it comes here |
|---|---|---|
| 1 | Design, quotes and approvals | Decisions on layout and floors affect every trade after |
| 2 | Hacking and demolition | The messiest step; must be finished before anything new goes in |
| 3 | Structural, extension and wet works | Kitchen and bathroom waterproofing and tiling, extensions |
| 4 | M&E rough-in | Wiring, plumbing and aircon piping in walls, ceilings and floors |
| 5 | Plaster ceiling and partitions | Dusty overhead work, best before finishes |
| 6 | First coat of paint | Heavy painting before the floor goes down |
| 7 | Flooring | Installed on a clean, prepared base, then protected |
| 8 | Carpentry and built-ins | Kitchen cabinets, wardrobes, TV feature walls |
| 9 | Stairs | Treads and nosings finished to match the floors |
| 10 | Final paint, lights and fittings | Touch-ups once carpentry is done |
| 11 | Outdoor works | Porch, decking, artificial grass, gate and fence |
| 12 | Final clean and handover | Protection removed, snag list checked |
Steps 1–5: Getting the Messy Work Done
Plan floors early. Decide which rooms get which flooring at design stage. Floor height matters: tiles, SPC and vinyl all have different thicknesses, and transitions between rooms, doors and stairs need planning. If you plan to keep the old tiles and lay SPC over them, that affects door clearances too. Our guide to laying SPC over existing tiles explains what to check.
Hacking and wet works. Hacking old tiles, walls or kitchens creates a lot of dust and debris. Kitchen and bathroom waterproofing and tiling are wet trades that should finish before the main floor goes in.
M&E and ceilings. Electricians, plumbers and aircon installers often need to run pipes and cables through floors and walls. Plaster ceiling work drops dust everywhere. All of this is better done before the new floor arrives.
Step 6–7: Paint, Then Flooring
Most contractors do the first full coat of paint before flooring, because ladders, rollers and drips are hard on a new floor. Final touch-ups happen later, with the floor protected.
Flooring then goes onto a clean, prepared base. For floating floors such as SPC, the installer will check that the base is flat and dry, then lay underlay and planks. Our guide to the installation process explains what usually happens on the day.
Step 8: Carpentry and Built-Ins
Here there is a choice to make with your carpenter and flooring installer:
- Floor first, cabinets on top: common with glued floors and lighter built-ins.
- Cabinets first, floor fitted around: often preferred with floating floors under heavy kitchen cabinets and full-height wardrobes, so the floor can still move and planks can be replaced.
Either way, agree it before ordering, because it affects quantities, kick-board heights and skirting.
Not sure whether cabinets or flooring should go first?
WhatsApp us your kitchen and wardrobe plans. We’ll explain the options for your floor type.
Step 9: Stairs
Stairs are usually finished after the main floors so the treads and nosings match in colour and height. Plan the stair finish together with the floor at design stage, especially if you want the same wood look upstairs and down.
Step 10–11: Final Touches and Outdoor Works
Final painting, lights and fittings happen with the floor covered. Outdoor works such as porch tiles, decking and artificial grass often come near the end, partly because heavy materials and machinery pass through the porch during the main renovation.
For outdoor surfaces, see our guides to outdoor decking and artificial grass.
Protecting the New Floor Until You Move In
- Cover the floor with protection sheets or boards as soon as it is installed
- Tape protection at the edges so dust and paint do not get under it
- Ask all trades to use drop cloths and soft-wheeled trolleys
- Keep heavy materials off finished floors where possible
- Remove protection only for the final clean
- Do a walk-through and snag list before handover
For room-by-room decisions on living areas, bedrooms, kitchens, stairs and outdoor spaces, see our room-by-room guide for landed homes. To see the options we install, visit our SPC flooring page, or contact us to arrange a site visit.
FAQ
When should flooring be installed in a house renovation?
Usually after hacking, wet works, wiring, plumbing, plaster ceiling and the first coat of paint, and before or around carpentry. The exact order depends on your floor type and built-ins.
Should kitchen cabinets go on top of the new floor?
It depends. With floating floors such as SPC, heavy cabinets are often installed first and the floor fitted around them. Discuss with your installer and carpenter before ordering.
Should painting be done before or after flooring?
Most contractors do the main painting before flooring and final touch-ups after, with the floor protected.
When are stairs done in a renovation?
Usually after the main floors, so treads and nosings can match the floor colour and finished height.
How do I protect new flooring during renovation?
Cover it with protection sheets or boards immediately after installation, tape the edges and keep it covered until the final clean.
Plan Flooring for Your Renovation
Send us these on WhatsApp and we’ll reply with the next steps:
- Your area (e.g. Shah Alam, Klang, Puchong, Subang)
- House type (terrace, semi-D, bungalow)
- Rooms to floor and approx sqft
- Current floor (tiles, cement, marble, other)
- Your contractor’s rough timeline, if you have one
- 2–3 photos of the house
What happens after you WhatsApp us
Reply → site visit → timing → quote
- We reply with questions about your renovation.
- We arrange a site visit in the Klang Valley to measure and check the base.
- We suggest where flooring fits in your order of works.
- We send a quote with preparation, installation, trims and stairs listed.
Indoor flooring, stairs, decking and artificial grass across the Klang Valley.